Berlin Brandenburg airport passenger Terminal 1 approved for use

Share

The Dahme-Spreewald administrative district’s local building inspection authority confirmed the completion of the passenger terminal (Terminal 1) at BER following completion of the construction work.

Below you will find the joint press release from the Dahme-Spreewald administrative district and Flughafen Berlin Brandenburg GmbH.

Commissioning of the airport in Schönefeld secured from the building authorities

The Dahme-Spreewald administrative district’s local building inspection authority confirmed the completion of the passenger terminal (Terminal 1) at BER following completion of the construction work. After months of the specialist authority checking the documents for construction completion submitted since 2019 by the building owner, Flughafen Berlin Brandenburg GmbH (FBB), there is now nothing to prevent it from being used as a passenger terminal with the commissioning of BER Airport in Schönefeld scheduled for 31 October 2020.

The granted approval for use is a milestone for the opening of BER. “I am very pleased that the ‘passenger terminal’ construction site is finally being completed after years of construction work and that evidence for the safe use of the building is available”, says Dahme-Spreewald’s building regulation coordinator, Heike Zettwitz.

Airport CEO Prof. Dr.-Ing. Engelbert Lütke Daldrup also sees the approval for use of the Terminal 1 building as one of the most important steps on the way to reliably commissioning BER. “It was a long and difficult road to the final approval from the building authorities. The last three years of hard work have finally paid off. I would like to thank everyone who has not given up on BER and those who have made the passenger terminal a safe building little by little thanks to their great personal commitment and perseverance. The opening of BER can be a signal during these times that things are looking up again in the capital region and that the economy is getting back on its feet,” say the FBB Chief Executive Officer.

The operating company FBB can now start preparations for trial operations (ORAT programme), which will be being carried out alongside some ongoing remaining construction work. ORAT stands for “Operational Readiness and Airport Transfer”, which is an internationally established standard procedure for partially testing practical procedures before new airports are commissioned. In the meantime, interior construction for shops, restaurants and a lounge will be carried out over the next few months for passenger terminal tenants and the elimination of minor structural defects will be completed, says the Building Regulations Department. Separate aviation law-related approvals are required for the opening of Schönefeld’s BER Airport. This is not the responsibility of the local building inspection authority but rather the Joint Aviation Authority Berlin-Brandenburg (LuBB).

28.04.20 17:30

This post was published on 1 May 2020 14:42

André Orban

M. Sc. Engineering

Published by
André Orban

Recent Posts

Condor launches daily Berlin–Abu Dhabi flights with Etihad codeshare

Condor has launched daily flights between Berlin Brandenburg and Abu Dhabi, operated in codeshare with…

16 October 2026

Delta to launch daily Boston–Reykjavík flights in April 2027

Delta Air Lines will introduce daily seasonal flights between Boston and Reykjavík Keflavík on 12…

16 October 2026

Saab unveils Sweden’s first GlobalEye surveillance aircraft

Saab has presented the first GlobalEye airborne early warning and control (AEW&C) aircraft for the…

16 October 2026

Air India Frankfurt–Delhi flight diverts to Jaipur after suspected accidental hijack alert

Air India flight AI2030 from Frankfurt to New Delhi (Boeing 787-9 registered VT-TSE) diverted to…

16 October 2026

easyJet adds five UK routes for summer 2027, including three from Southampton

easyJet has put five additional UK routes on sale for summer 2027, following the 18…

16 October 2026

Lufthansa Cargo expands Asian links and shifts Mumbai freighters to Navi Mumbai

Lufthansa Cargo’s winter 2026/27 schedule will offer 88 freighter routes serving 40 destinations worldwide, with…

16 October 2026