Amsterdam Schiphol runway 18C-36C (Zwanenburgbaan) available again for air traffic after major maintenance

Share

As of today, the Zwanenburgbaan Runway (18C-36C) is available again for air traffic after a period of major maintenance. This maintenance will ensure that the runway can continue to be used safely over the coming years. The runway can be fully deployed at times of good visibility, only not yet for landings from the south when visibility is limited. Before that can happen, test flights need to be carried out (on 13, 15 and 20 May) to check the renewed Instrument Landing System (ILS), and after that, there’s a validation period of at least thirty days.

During this period of major maintenance, work was carried out that is necessary every 40 to 60 years in order to ensure that travellers can fly safely. The work included renewing the asphalt on the runway – an area equal to 86 football pitches. 60% of the asphalt was reused during this upgrade.

Schiphol also renewed 12,000 square metres of markings on the runway and replaced 6 kilometres of guttering and drains on and around the runway. The runway lighting and corresponding electric cables were replaced by a more sustainable and reliable LED lighting system. The works were carried out in collaboration with the construction company Heijmans.

Instrument Landing System test flights 
During the period of maintenance, Air Traffic Control the Netherlands (LVNL) updated the ILS on the northern section of the runway. An ILS helps aircraft to make a gradual approach towards the runway. Some of the work that needs to be carried out on the ILS, such as measurements and test flights, can only take place once the major maintenance is complete. While the measurements and test flights are carried out on 13, 15 and 20 May, the runway will be unavailable for air traffic for a few hours.

As of today, the Zwanenburgbaan Runway can be deployed at times of good visibility. It is still not possible for aircraft to land from the south when visibility is limited, such as when there’s thick fog. According to international safety standards, the new ILS must have been working reliably and stably for thirty days before the Zwanenburgbaan Runway can be deployed again in all visibility conditions.

4 May 2023

This post was published on 5 May 2023 12:37

André Orban

M. Sc. Engineering

Published by
André Orban

Recent Posts

Lufthansa schedules first A350-1000 passenger flight to Tokyo on 3 December

Lufthansa plans to introduce its first Airbus A350-1000 on the Munich–Tokyo Haneda route on 3…

15 October 2026

EUROCONTROL’s Maastricht centre more than halves summer air traffic delays

EUROCONTROL’s Maastricht Upper Area Control Centre (MUAC) handled 842,259 flights between May and September 2026,…

15 October 2026

LOT parent plans dedicated cargo airline under new growth strategy

Polska Grupa Lotnicza (PGL), the aviation group behind LOT Polish Airlines, plans to establish a…

15 October 2026

airBaltic aircraft lands safely at Brussels Airport following technical emergency

An airBaltic A220-300 aircraft registered YL-ABS arriving from Berlin as flight SN2590 on behalf of…

15 October 2026

Norwegian expands UK–Oslo flights to support Norway’s ski tourism push

Norwegian Air Shuttle is increasing winter capacity between the UK and Oslo as part of…

15 October 2026

Brussels Airport adds four destinations to winter network of 136 routes

Brussels Airport will offer 136 direct destinations during its winter season starting on 25 October,…

15 October 2026